Frequently Asked Questions

I want to have an elevator, what is the price?
 
Elevators do not have a fixed price. It depends on the properties of the building and the elevator to be built.
 
The class of the building is a new design based on the features such as the capacity, speed, door type, etc., and pricing can be done after pricing in accordance with this design.
  
 
How can I determine the number and properties of elevators that will determine the exact need of my building?
 
During your project, Elevator Traffic Calculation must be made in accordance with the usage area of ​​the building and the number of floors. After an Elevator Project is drawn up in accordance with the Elevator Traffic Account, this process will be clear. Preliminary projects must be drawn by elevator firms or Electrical and Mechanical Project offices by an engineer with an authorized SMM certificate on Elevator.
 
 
What should be the height of the Vault Concrete in the Elevator Machine Room?
 
The height of the vault concrete from the floor of the engine room is not standard. The correct reference here is not the engine room base.
 
The last floor of the elevator must be 3700 mm from the ground level. Therefore, it may vary depending on the floor height of your project.
 
This distance may vary for elevators of different speeds and capacities. You can always find the right size in the dimensions section of our page.
 
 
What should be the pit depth of the elevator?
 
The elevator pit depth should not be less than 1400 mm in accordance with the standard. You can reach this measurement, which varies according to speed and capacity, in the dimensions section of our page. In home lifts, solutions can be produced even at 200 mm thanks to special systems, but for these special solutions, you must contact our company.
 
 
At which stage of the construction must an agreement with the elevator company?
 
It will be the right time to make an agreement with the elevator company when the plaster starts after the rough construction is finished. The elevator door edges in landings
 
plaster and coating works will not walk unless installed, and the flow of your works will slow down.
 
 
How many months does the assembly of the lift complete after the agreement is made?
 
Completion of the elevator is approximately 3 months according to our contract period. Manufacturing and procurement process is quite high in factories rather than assembly of the elevator in construction. But it should not be forgotten that the end of the elevator is directly proportional to the end of the building.
 
Unless the door edge modifications and landings of the landings are made, assembly of the lift cannot be completed. As the elevator company, we become the last team to leave your building. While fine cleaning operations are done, the last adjustments and cleanings of the elevator are also made.
 
 
When does the warranty period start working?
 
When the lift is installed and the license is obtained, the warranty period starts when the elevator is given to the service. The time between obtaining a license and giving it to the service may be a long time. During this time, the elevator is not operated. When the building management is formed and the Maintenance Contract is signed, after a final cleaning and adjustments are made, in the building management, that is, the warranty period starts from the moment the elevator is delivered to the end users.
 
 
Is it possible to start the elevator with construction site electricity?
 
Yes it is possible, but it is risky. All malfunctions occurring during use with site electricity are covered by the warranty and are the responsibility of the person keeping them open for use. It is legally prohibited to operate the lift without connecting electricity from TEK.
 
 
What is the work flow plan of the elevator assembly?
 
After the agreement is completed, the projects are drawn and the rail door assembly is done in the first place. If the engine room construction works have been completed, the machine engine assembly can also be done. After these processes are finished, installation is interrupted for rough construction and modification works. After the door edge renovations and landing floors are finished, the cabin table installation and processes, which we call fine works, continue.

 